Get a quote

Crossways & Network Rail

PROBLEM
Network Rail needed to effect repairs to a mainline rail bridge over the River Derwent. In order to undertake this, a complex scaffold structure needed to be erected from underneath the bridge to keep the rail line open.

SOLUTION
Contractors requested an 8m x 4m Scafffloat with a 50Hp engine and 3 tonne payload to carry scaffolders and equipment to any point under the bridge. The solution was further enhanced by the provision of an unpowered 4m x 4m Scafffloat platform which was connected to the bow of the main ScaffFloat and then detached and positioned immediately where work was taking place to allow direct access to the low structure once scaffolding was in place.

Gallery

An 8x4m ScaffFloat with platform and outboard to install scaffolding under a railway bridge
Installing scaffolding on a railway bridge from a 8x4m ScaffFloat pontoon
8x4m ScaffFloat steaming with safety boat

Related case studies