Problem

 

GPS MACS required floating access on a narrow concrete-lined drainage channel in Tottenham, London 

 

Solution

 

ScaffFloat mobilised 6no 8 x 4.2m pontoons, which were moored in the channel, which was split down the middle by a mid-channel wall. A bridge was then used to provide safe access over the mid-channel wall, connecting the two rows of pontoons. 

 

Our team mobilised and installed the pontoons in their location, which required drilling and bolting in the mooring points. They then handed the pontoons over to the client for the duration of the project.