River Cam – Cambridge
PROBLEM
Attridge Scaffolding were asked to build a crash deck under a bridge in Cambridge. This was needed for repair works being carried out by Balfour Betty for Network Rail.The river is heavily used by rowers and pleasure craft so it was not an option to close the waterway.
SOLUTION
– We mobbed an 8m x 4m ScaffFloat with spud legs to hold it in position under the bridge, a small 15hp outboard to position it and a skipper to operate it and warn oncoming traffic.
– Scaffolders loaded the pontoon with scaffold and then worked from the pontoon to install the scaffold. This saved significant time for the client.