Chetwynd Bridge
PROBLEM
The local authority needed to inspect a busy road bridge for excessive movement over the fast flowing and very shallow River Tame. Targets needed to be suspended accurately from the bridge structure in numerous locations for upcoming laser measurements.
We have been involved in this great project since the beginning, first giving floating access for surveys and inspections, then access to install scaffolding and now helping the team at Attridge Scaffolding Services strip it all out.
SOLUTION
An 8m x 4m unpowered ScaffFloat with a lightweight, adjustable, scaffold tower was provided complete with crew. The ScaffFloat was manoeuvred with a mix of ropes running across the river and a powered winch arrangement allowing for the float to be pulled against and across the current to reposition.
Crew were enabled access on and off the ScaffFloat through the use of a shallow draft safety boat to and from the river bank. The ScaffFloat positioning was remarkably precise using ropes, but further anchoring capability was provided through the use of spud legs.
The job was completed quickly and without any issues, well ahead of schedule.