Get a quote

Scour Protection – Camarthen, Wales

Problem

Northern Divers required a self-propelled pontoon with a Hiab crane to support the installation of 14 x 700kg rock bags to provide scour protection to an exposed pipeline in the River Towy near Carmarthen.  

Solution

ScaffFloat mobilised an 8m x 6.4m self-propelled pontoon with twin 60hp high thrust outboards and a 2.8 tonne Hiab crane with a 6hp hydraulic power unit. Launched from a site downriver of the pipeline, the skipper and crew would steam to the site and back again every day, working on site over the low tide. The Hiab crane, with support from the divers in the water, was used to lift the rock bags from the deck of the ScaffFloat into position over the pipe. Due to the range and flow of the tide the team was restricted in when they could return back to their mooring each night.  

While on site, the ScaffFloat was held in position using a bridle of anchors and spud legs. 

Testimonial 

“Thank everyone for their fantastic efforts and perseverance with the River Towy project. It was thought to be a reasonably straightforward project, but Mother Nature and the logistics certainly proved otherwise. Great job, guys, and many thanks to all involved.” Martin Shepherd, Diving Manager, Northern Divers.

Gallery

Scour Protection, Camarthen

Related case studies

River Lea

GPS MACS required a floating platform with lifting capabilities that could dry out on the steep mud banks of Thames to install ladders and fendering.

Read More: River Lea